工作流笔记(三)

Posted by Nino Lau on April 11, 2019

A secret project by the government (let’s call it Project X) will be executed by one person and consists of 6 tasks: A, B, C, D, E, and F. Figure 2.28 specifies the order in which the tasks need to be executed (precedence graph, cf. PERT/CPM). A possible execution trace is for example ABDCEF.

(a) Model the project in terms of a classical Petri net.

(b) How does one model so that E is optional?

(c) How does one model so that D and E should be executed consecutively, that is, B and C are not allowed between D and E?

R2


  1. ans1
  2. ans2
  3. ans3